As-Planned vs. As-Built: Reading the Variance Correctly
Float absorption is not delay. When an activity finishes later than its as-planned baseline but still had total float remaining, that slippage never pushed the project’s finish date -- the float simply absorbed it. Only slippage that consumes an activity’s float entirely, and then keeps going, translates into real project delay.
The Error This Catches
A bar chart is a dangerous thing to eyeball. Overlay an as-built schedule on an as-planned baseline and almost every non-critical activity will show some bar sliding right of where it was supposed to land -- that’s normal, expected variance, not evidence of delay. The question a bar chart alone can’t answer is whether a given activity had float to spare when it slipped. An activity can finish two weeks late and still never have become critical; another can finish a few days late and drive the finish date directly, because it had almost no float left to give.
Pointing at a late-finishing bar and calling it “delay” without checking its total float first is one of the most common -- and most avoidable -- mistakes in reading a schedule comparison.
Worked Example: A Retail Fit-Out, Two Activities Slip
A seven-activity retail fit-out package, baselined against a planned Substantial Completion of April 5. The critical path runs Mobilization → Demolition → Drywall & Framing → Flooring → Final Inspections. Two other activities run in parallel with float relative to that path: MEP Rough-In (15 days of float) and Millwork Fabrication & Install (3 days of float). Both finish late in the field.
- C — MEP Rough-In. Planned finish Feb 14, carrying 15 days of total float because flooring installation doesn’t actually need it complete until March 1. It finishes 8 days late, on Feb 22. That leaves 7 days of float still unused -- MEP rough-in never became critical, and Flooring starts exactly on its planned date.
- E — Millwork Fabrication & Install. Planned finish March 18, carrying only 3 days of total float, because Final Inspections can’t start until millwork is in place. It finishes 10 days late, on March 28 -- consuming all 3 days of float and then overrunning by 7 more. Final Inspections, planned to start March 22, can’t start until March 29 as a result -- a 7-day push straight through to Substantial Completion.
| Code | Activity | Planned Finish | Actual Finish | Original Float | Delayed Project? |
|---|---|---|---|---|---|
| A | Mobilization & Permitting | Jan 15 | Jan 15 | 0d | No |
| B | Interior Demolition | Jan 25 | Jan 25 | 0d | No |
| C | MEP Rough-In | Feb 14 | Feb 22 | 15d | No |
| D | Drywall & Framing | Mar 1 | Mar 1 | 0d | No |
| E | Millwork Fabrication & Install | Mar 18 | Mar 28 | 3d | Yes |
| F | Flooring Installation | Mar 21 | Mar 21 | 0d | No |
| G | Final Inspections & Substantial Completion | Apr 5 | Apr 12 | 0d | Yes |
C and E both finish late. Only E’s slippage shows up again downstream, on G.
Reading it correctly
C’s 8-day slip and E’s 10-day slip look similar on a raw as-planned-vs-as-built bar chart -- both are simply “late.” They are not the same event. C had 15 days of float and used 8 of them: the activity never became critical, nothing downstream moved, and the project’s Substantial Completion date is unaffected. E had only 3 days of float and used all of it, then kept slipping for 7 more days it didn’t have: those 7 days had nowhere to go but straight into the project finish date. Final Inspections (G) shows exactly a 7-day push in the table above -- not 10, and not 0 -- because the first 3 days of E’s slip were already spent before the project felt anything.
The project was delayed by 7 days, entirely attributable to activity E. Activity C’s 8-day slip, despite being the more dramatic-looking bar on a chart sorted by variance, contributed zero days of actual delay.
Claims Digger tracks each activity’s total float across every schedule update you upload. Instead of eyeballing a bar chart and guessing, you can see directly whether a given activity’s slippage was absorbed by its own float or actually consumed it and pushed the finish date -- for every activity, on every update, not just the two in a worked example. See how it works.
Frequently Asked Questions
- If an activity finishes later than the baseline planned, isn't that always a delay?
- No -- and treating it that way is one of the most common analytical errors in delay claims. A late finish only becomes project delay once it consumes the activity's total float and pushes a downstream date, typically the project's finish. An activity with float remaining can finish late and still have never become critical.
- What happens to an activity's remaining float once part of it is consumed?
- Its total float shrinks by the number of days consumed. An activity that starts with 15 days of float and finishes 8 days late is carrying roughly 7 days of float into the next schedule update, not 15 -- the update should reflect that narrower cushion, not treat the activity as still having its original float.
- Does this analysis require a fixed as-planned baseline, or can it be done from progress updates alone?
- It requires a baseline. Total float and "planned finish" are baseline concepts -- without a fixed reference point to compare actual dates against, there's nothing to measure the variance from, and no way to tell float absorption apart from real delay.
- How does float absorption relate to concurrent delay?
- They're closely related ideas built on the same foundation. Just as a late-finishing activity with float remaining never delayed the project, a delay event sitting on an activity with float to spare never became independently critical -- so it can't be concurrent with anything either. See our companion article on testing for concurrent delay.