Time Impact Analysis, Step by Step

Time Impact Analysis (TIA) is the forensic-scheduling method for measuring exactly what a single delay event does to a project’s finish date -- by inserting a fragnet into the schedule and recalculating the network. Here’s the full method, worked through on a fictional 13-activity build-out from baseline to time extension.

What TIA Is, and When It’s Used

TIA is a prospective method -- it doesn’t wait until a project is finished to reconstruct what happened. Instead, it takes the accepted schedule update from immediately before a specific delay event occurred, builds a small sub-network called a fragnet (fragmentary network) that models the delay event’s own logic and duration, splices that fragnet into the schedule at the exact point the delay actually intercepted the work, and recalculates the entire network forward. Whatever shift appears at the project’s critical path and completion milestone is the delay event’s measured time impact -- nothing else changes between the two runs.

It’s the method both AACE International (Recommended Practice 52R-06) and the SCL Delay and Disruption Protocol document as the preferred approach for evaluating a time-extension request while the project is still underway, precisely because it isolates one event’s effect without needing to wait for -- or rely on -- how the rest of the project actually played out afterward.

The Baseline Schedule

Thirteen activities for a fictional interior office build-out, data date Day 0. Rough-in work runs in three parallel trades after demolition; HVAC is the longest of the three and, along with the finish-out sequence behind it, drives the 51-workday baseline finish (highlighted rows below).

CodeActivityDurationPredecessor(s)Baseline Span
APermits & Mobilization5 d—Day 0–5
BDemolition5 dADay 5–10
CPlumbing Rough-In8 dBDay 10–18
DElectrical Rough-In9 dBDay 10–19
EHVAC Rough-In10 dBDay 10–20
FWall Framing & Insulation6 dC, D, EDay 20–26
GDrywall, Tape & Finish7 dFDay 26–33
HInterior Doors & Millwork6 dGDay 33–39
IFlooring5 dGDay 33–38
JPainting5 dH, IDay 39–44
KFinal MEP Trim & Fixtures4 dJDay 44–48
LPunch List & Owner Walkthrough3 dKDay 48–51
MSubstantial Completion—LDay 51–51

Highlighted rows (A, B, E, F, G, H, J, K, L, M) form the baseline critical path -- zero float, finishing Day 51. C (2 days of float), D (1 day), and I (1 day) are near-critical but not driving.

The Delay Event and the Fragnet

On Day 26 -- the moment Wall Framing & Insulation (F) actually finished, and the schedule update immediately before anything went wrong -- the owner issues a directive relocating the electrical panel room to accommodate a last-minute change to the tenant’s server-rack layout. Drywall (G) can’t proceed until revised drawings are approved and the affected framing is reworked. That’s an owner-caused delay event, and it needs a fragnet: three new activities, logically tied in exactly where the delay actually intercepted the work, between F and G.

CodeFragnet ActivityDurationSpan
NOwner Review & Approval — Revised Panel Room RFI10 dDay 26–36
ORevise Electrical & Framing Drawings3 dDay 36–39
PField Rework — Reframe Panel Room Wall4 dDay 39–43
FG (baseline: Day 26–33)Baseline link (superseded)FDay 20–26NOwner reviewDay 26–36ODay 36–39PDay 39–43GDay 43–50+17 workdays
Ghosted top: the baseline link, F straight into G on Day 26. Solid bottom chain: the recalculated network, with the N-O-P fragnet spliced in at that same point, pushing G’s actual start to Day 43.

The Recalculated Network and the Time Extension

Activities A through F are untouched -- the delay happens after F finishes, so nothing before Day 26 changes. Running the forward pass again with N, O, and P inserted shifts every downstream activity by exactly 17 days, because the fragnet lands on what was already the zero-float critical path and no other path (C at 2 days of float, D at 1, I at 1) comes close to absorbing 17 days of it:

CodeActivityBaseline SpanRecalculated Span
GDrywall, Tape & FinishDay 26–33Day 43–50
HInterior Doors & MillworkDay 33–39Day 50–56
IFlooringDay 33–38Day 50–55
JPaintingDay 39–44Day 56–61
KFinal MEP Trim & FixturesDay 44–48Day 61–65
LPunch List & Owner WalkthroughDay 48–51Day 65–68
MSubstantial CompletionDay 51–51Day 68–68
BaselineDay 51RecalculatedDay 6817-day extension
Every tail activity (G through M) shifts by the same 17 workdays as the fragnet itself -- confirming the delay passed straight through to the finish date with no float absorbing any part of it.

Time extension = Recalculated finish − Baseline finish = Day 68 − Day 51 = 17 workdays. Because the fragnet fell on the update’s existing critical path and every parallel path had less float than the fragnet’s 17-day duration, the full fragnet duration flows through unabsorbed. That won’t always be true -- a fragnet landing on a path with more float than its own duration would show a smaller extension, or none at all.

Doing this on paper for a 13-activity example is manageable. On a real, multi-thousand-activity schedule with dozens of updates, it isn’t. Claims Digger’s schedule comparison shows exactly which activities shifted onto or off the critical path between any two updates, with the specific date and duration changes driving that shift laid out side by side. See how it works.

Frequently Asked Questions

How is Time Impact Analysis different from a retrospective, as-built delay analysis?
TIA is prospective. It takes the schedule update from immediately before the delay event, inserts a fragnet to model the event, and recalculates forward to see what the network itself predicts about completion -- rather than reconstructing the critical path after the fact from as-built dates once the project (or the disputed period) is already over.
Does the TIA have to be prepared at the moment the delay happens?
Ideally yes, or as close to it as practical -- that contemporaneity is a big part of what makes the projected impact credible. Many contract forms (including common federal and design-professional contract templates) set specific windows for submitting a time-extension request built on a TIA, though analysts sometimes have to reconstruct one later using the update that would have been current at the time.
What if the fragnet doesn't land on an activity that's already critical?
Then the network recalculation may show a smaller time extension than the fragnet's own duration, or none at all, if there was enough float on that path to absorb it. A time extension exactly equal to the fragnet's duration -- like in the worked example above -- only happens when the delay lands on a path with little or no float to spare.
Who has to agree on a TIA before it's binding?
A TIA is normally prepared by the contractor's scheduler and submitted to the owner or construction manager for review; it typically isn't a unilateral entitlement until the reviewing party accepts the logic, durations, and fragnet placement, or it's resolved through whatever contract mechanism governs disputed time-extension requests.

Part of the Claims Digger Learning Center. Related reading: Concurrent delay: how to actually test for it · Full glossary