Feature
Collapsed As-Built / But-For
Remove a delay from a finished schedule and see when it would have finished.
What it does
Starts from a completed (or largely complete) schedule, sets the chosen excusable delay activities to zero duration, rebuilds the network from its logic and as-built durations, and reports how much earlier the project would have finished without them. The delay is measured against a rebuild of the same schedule with nothing removed, so systematic differences between real dates and logic don't get blamed on the delay.
What it helps you achieve
- Estimate the time attributable to specific events after the fact.
- See which activities would have moved, by how much, and how the finish changes.
- Understand how far the recorded dates depart from the schedule's own logic.
How to run it
Where to find it: Project page → Collapsed As-Built
- Open the project and choose Collapsed As-Built, then + New CAB analysis.
- 1. Choose the as-built schedule: a complete or substantially complete update.
- 2. Choose the excusable delay activities to collapse (only completed activities are offered).
- Choose Run Analysis.
- Read the four figures: As-Built Finish (real dates), Rebuilt Finish (nothing collapsed), But-For Finish (collapsed) and the delay attributable.
- Review the table of activities that shifted, and the Gantt overlay showing the but-for position.
What you get
- As-built, rebuilt and but-for finish dates side by side.
- The delay in calendar days and working hours.
- A per-activity table of how far each moved.
- A disclosed 'logic gap': how far the real finish sits from a logic-only rebuild.
- An Excel export and a saved, reopenable result.
Good to know
- A collapsed activity is set to zero duration and kept in the network, so the schedule's sequencing is preserved. It is not deleted and re-linked, which would require guessing how to reconnect its neighbours.
- A negative or unexpected result usually says something about the schedule, not the delay; the logic-gap note is there to show exactly that.
Limits, stated plainly
- It needs completed work. When fewer than 90% of activities are complete, a warning explains that the result reflects only the work finished so far.
- Only completed activities can be collapsed, because an unfinished one has no as-built duration to remove.
Try Collapsed As-Built / But-For on your own schedules. Claims Digger is invite-only while we’re in early access.
Request accessFrequently asked questions
- Why measure against a rebuild rather than the real finish date?
- Recorded dates rarely follow a schedule's logic exactly (out-of-sequence work, waiting no relationship captured). Comparing a logic-only recalculation with the real dates would blame that gap on the delay you removed. Measuring against a rebuild with nothing removed cancels it, and the gap is reported separately.