Lags (positive lag)

Relationships that build a waiting period into the logic.

Threshold0

What it measures

How many relationships carry a positive lag.

How Claims Digger calculates it

Counts relationships with positive lag among those whose successor isn't yet complete. Any lag at all is flagged; the check passes only at zero.

Why it matters

A lag is time in the schedule that isn't represented as an activity anyone can track, status or update. It is schedule risk hiding in a relationship.

How to fix a failure

  • Replace each lag with a real activity (for example 'concrete cure') so it has a duration, a calendar and a status.
  • Keep a lag only where it is a true fixed delay with no work behind it, and be prepared to explain it.