DCMA-14 · Check 3 of 14
Lags (positive lag)
Relationships that build a waiting period into the logic.
Threshold0
What it measures
How many relationships carry a positive lag.
How Claims Digger calculates it
Counts relationships with positive lag among those whose successor isn't yet complete. Any lag at all is flagged; the check passes only at zero.
Why it matters
A lag is time in the schedule that isn't represented as an activity anyone can track, status or update. It is schedule risk hiding in a relationship.
How to fix a failure
- Replace each lag with a real activity (for example 'concrete cure') so it has a duration, a calendar and a status.
- Keep a lag only where it is a true fixed delay with no work behind it, and be prepared to explain it.