Every DCMA-14 check, explained

The DCMA 14-point assessment scores a schedule’s structure. Each check below has its own page: what it measures, the threshold, exactly how Claims Digger calculates it, why it matters, and how to fix a failure. For the overview, read the complete assessment explained.

  1. 1.Logic (missing predecessors and successors)

    Threshold: < 5%

    The share of incomplete tasks with no predecessor or no successor.

  2. 2.Leads (negative lag)

    Threshold: 0

    Relationships that let the successor start before its predecessor logic would permit.

  3. 3.Lags (positive lag)

    Threshold: 0

    Relationships that build a waiting period into the logic.

  4. 4.Relationship types

    Threshold: FS 90% or more, SS + FF under 10%, SF = 0

    The mix of Finish-to-Start, Start-to-Start, Finish-to-Finish and Start-to-Finish relationships.

  5. 5.Hard constraints

    Threshold: < 5%

    Incomplete tasks with a Mandatory Start or Mandatory Finish constraint.

  6. 6.High float

    Threshold: < 5% (over 44 days)

    Tasks with more than 44 days of total float.

  7. 7.Negative float

    Threshold: 0

    Any activity with total float below zero.

  8. 8.High duration

    Threshold: < 5% (over 44 days)

    Incomplete tasks with an original duration over 44 days.

  9. 9.Invalid forecast dates

    Threshold: 0

    Dates that don't line up with the schedule's own data date.

  10. 10.Missing resources

    Threshold: < 5%

    Incomplete tasks with no resource assigned.

  11. 11.Missed tasks

    Threshold: 0

    Activities whose baseline finish has passed but which haven't finished.

  12. 12.Critical path test

    Threshold: Connected

    Whether the activities P6 marked as driving form one connected chain.

  13. 13.CPLI (Critical Path Length Index)

    Threshold: 0.95 or higher

    How much float the critical path has relative to its length.

  14. 14.BEI (Baseline Execution Index)

    Threshold: 0.95 or higher

    How much of the work planned to be done by now is actually done.